Already the first Russian attacks showed the vulnerability of such a model. Strikes on large TPPs or key substations could simultaneously disable significant volumes of generation or complicate the delivery of current to consumers.
Context
In the summer of 2024, after Zelensky announced plans to build a "presidential gigawatt", the country finally approached the construction of a new maneuverable generation. Initially, the program was gaining momentum: companies announced new projects and purchased equipment.
Volodymyr Kudrytskyi, the former head of Ukrenergo, has repeatedly called the same 700 MW in various broadcasts. "Our consumption in the cold winter is 15-18 thousand megawatts in the evening, the deficit last year, which was voiced by Zelensky, is 7 thousand megawatts, 700 megawatts have been built. Is it a lot or a little?" Kudrytskyi asked.
What's next
At the same time, the power system did not count not only the installations that the business planned to launch, but also the equipment that was transferred to cities and communities free of charge by international partners.